Cpk in Injection Molding: How to Read a Supplier’s Capability Data

HOME BLOG

How TONGDA LINK structures per-cavity capability reporting for medical-device programmes — and what to check before you accept a supplier’s number.

A supplier tells you their process holds Cpk 1.67. That single number can mean “we run a stable, well-controlled process” — or “we measured 30 parts off a freshly tuned machine on a good day.” Here is how to tell which one you are looking at — written from the shop-floor side at TONGDA LINK, where we run these studies on medical and precision tooling every week.

→ For realistic tolerance ranges on plastic parts, see our guide on

What the Numbers Actually Measure

  • Cp = (USL − LSL) / 6σ — spread only. It ignores whether the process is centred.
  • Cpk = min[(USL − μ)/3σ, (μ − LSL)/3σ] — spread and centring. This is the number that matters.
  • Pp / Ppk — same maths, but using overall (long-term) variation rather than within-subgroup variation. Ppk is normally used for initial process studies, before the process is proven stable.

A part can have excellent Cp and poor Cpk: tight spread, wrong mean. On plastic parts this is common, because shrinkage pulls the mean away from nominal — and shrinkage is a range, not a constant.

The Thresholds Buyers Use

Cpk / Ppk Typical interpretation
≥ 1.67 Capable; commonly required for automotive and medical critical characteristics
1.33 – 1.67 Generally acceptable with continued control; often the baseline requirement
1.00 – 1.33 Marginal; expect out-of-spec parts without tight monitoring
< 1.00 Not capable of holding the tolerance consistently

These are industry conventions (AIAG / IATF practice), not universal law — the customer’s specific requirement governs.

Five Ways a Capability Report Can Mislead You

  1. Sample too small or too convenient. A capability index from 10–20 parts is not a capability index. Ask for the sample size, subgroup structure and time span.
  2. Only the “good” cavity reported. On multi-cavity tools, cavities differ. Ask for Cpk per cavity, not an average across cavities.
  3. Measured under favourable conditions. Parts measured hot, straight off the machine, or without agreed conditioning will look better than parts measured at the incoming inspection.
  4. No MSA behind it. If gauge repeatability is poor, the Cpk is measuring the measurement system, not the process. Ask whether GRR was performed.
  5. No re-validation after change. Material lot, resin supplier, machine, tool repair or a cavity polish all change the distribution. Ask how often capability is recalculated.

What to Ask For (With This Into The RFQ)

For each critical dimension: Cpk per cavity, based on at least 30 consecutive shots across 3 production runs, measured at 25 ± 2 °C / 50 ± 10 % RH after 24 h conditioning, using CMM, with X̄–R control charts, measurement method and gauge R&R results attached.

Why Cpk Matters More on Plastic Than on Metal

Metal parts are dimensionally stable once machined. Plastic parts drift: post-moulding shrinkage, moisture uptake in PA/PC/PBT, continued crystallisation, and stress relaxation all move dimensions after ejection. A process that shows Cpk 1.67 in week one can degrade as the tool wears or as the resin lot changes. So ask for capability over a sustained run, and for the plan to re-verify it.

See also: why plastic part dimensions change after 48 hours.

What TONGDA LINK Actually Reports (Medical-Device Projects)

For medical-device customers, TONGDA LINK does not report a single headline Cpk. We report per-cavity, per-feature data with the conditions attached, because a number without conditions is not auditable.

Typical results. On critical features of single-cavity and multi-cavity tools running for medical assemblies, our per-cavity Cpk values most commonly fall in the 1.33 ≤ Cpk < 1.67 band, with some features exceeding 1.67. We do not claim a blanket figure across all parts: the achievable index depends on the nominal dimension, the tolerance band, the resin, and the measurement method. Where a customer requires Cpk ≥ 1.67 on a given feature, we agree that target before cutting steel and design the gating, cooling and tolerance allocation accordingly — or tell you honestly that the tolerance needs to be relaxed.

The following is our standard deliverable set for regulated programmes; items marked required ship with every medical-tool FAI package at TONGDA LINK:

FAI first (required) — actuals per cavity and per feature, not pass/fail only.

Cpk per cavity (required) — not pooled across cavities, with sample size, subgrouping and run dates shown.

X̄–R control charts (required) from the validation run(s), so you can see stability, not just the index.

Drift study at 24 h / 48 h / 72 h (required) on the same samples, with deltas recorded — because a Cpk taken at 2 hours does not describe the part you receive at day three.

Measurement conditions written in (required) — ambient temperature/humidity, conditioning time, fixture or CMM, datum scheme and probe strategy.

MSA / gauge R&R (required) for each critical characteristic, so the index reflects the process, not the gauge.

Report ownership — each report carries tool ID, cavity map, run dates, operator and measuring-equipment ID, so an auditor can trace it back to the shot.

Beyond Cpk: IQ / OQ / PQ for Mould Acceptance

Cpk describes a dimension. It does not describe whether the tool, the machine and the process are locked down. For regulated programmes we support full process validation structured as IQ, OQ and PQ — the same three-stage logic your quality team uses for production equipment, applied to the mould and its moulding process.

IQ — Installation Qualification. Documented evidence that the tool and its installation match the design intent. Typically covers: tool identification and cavity count; steel and heat-treatment certificates; verification of slides, lifters and ejector stroke; thermocouple and hot-runner controller calibration records; machine tonnage, platen and nozzle compatibility; and confirmation that all sensors, interlocks and safety devices function as specified.

OQ — Operational Qualification. Establishing the working window and proving the process is repeatable within it. This includes a process-window study over melt temperature, mould temperature, injection speed/pressure, hold pressure and time, and cooling time; determination of upper and lower limits; generation of limit/boundary samples; and demonstration that the process returns to centre after a normal stop/start.

PQ — Performance Qualification. A sustained production run at nominal settings producing conforming product. Executed as e.g. three consecutive runs of 1000 shots each, with per-cavity dimensional results, Cpk/Ppk on agreed characteristics, visual and functional checks, packaging and labelling verification, and full lot traceability.

Re-validation triggers (change control). Capability and qualification are not one-time events. We define in advance which changes require re-qualification: resin grade or supplier change, material lot change where shrinkage differs, tool repair or cavity polishing, insert or core replacement, machine transfer, and any change to the measurement method.

Documentation. At TONGDA LINK, protocols are approved by the customer’s quality engineer before execution; reports include raw data, deviations and conclusions. 

What TONGDA LINK Provide

For every critical dimension agreed up front, we supply: FAI report per cavity + Cpk per cavity + X̄–R charts + 24/48/72 h drift study + MSA/GRR + IQ/OQ/PQ protocol and report (when required), reviewed with the customer’s quality engineer before mass production.
 
Want to know how to evaluate a mould supplier end to end? See how to evaluate an injection mould supplier in China.

FAQ

1. What Cpk is required for precision injection molding?

Cpk ≥ 1.33 is a common baseline; ≥ 1.67 is typically required for automotive and medical critical characteristics. At TONGDA LINK we treat the customer’s drawing requirement as governing, and agree the target per feature before cutting steel.

2. What is the difference between Cpk and Ppk?

Cpk uses within-subgroup (short-term) variation and assumes a stable process; Ppk uses overall variation and is normally used for initial process studies before stability is proven.

3. Why can a supplier show high Cpk but still ship out-of-spec parts?

Small or cherry-picked samples, single-cavity reporting, measurement under favourable conditions, poor gauge repeatability, or drift after material/tool changes. Always ask for per-cavity data, conditioning details and GRR.

4. How many parts are needed for a meaningful Cpk?

Common practice is at least 30 measurements per characteristic, grouped into subgroups over more than one run. TONGDA LINK’s standard is 30 shots per cavity across 3 runs, but we align the sample plan with the customer’s quality engineer before execution.

PEOPLE ALSO ASK

Get a Report You Can Audit

Ask TONGDA LINK for a sample FAI + Cpk package — redacted, but complete.
 